Mälarenergi combined heat and power plant, Västerås
Installation of a stainless steel air piping system, including primary and secondary supports and replacement of selected sections of existing pipework.
Installation of a stainless steel air piping system, including primary and secondary supports and replacement of selected sections of existing pipework.
Mälarenergi AB is a municipally owned utility that supplies electricity, district heating, cooling, broadband and drinking water, and provides wastewater services. Its combined heat and power plant in Västerås includes the Block 6 waste-to-energy unit and the biomass-fired Unit 7.
Block 6 processes approximately 480,000 tonnes of household waste, industrial waste and recycled wood each year. By introducing waste into its fuel mix, Mälarenergi reduced its reliance on peat and cut fossil CO₂ emissions by approximately 300,000 tonnes per year.
Project Scope
Our team installed a new stainless steel air piping system, including the pipe runs and their primary and secondary supports. The primary supports hold the pipework in position, while the secondary supports connect them to the plant structure.
The installation involved positioning and aligning the pipe runs and coordinating the placement of both types of support along the piping route. Our team also carried out general maintenance work at the facility.
The scope combined air piping installation, pipe support installation and general plant maintenance.