Karlskoga Energi & Miljö AB is a municipally owned utility that provides district heating, steam, electricity distribution, water and wastewater services, waste management and recycling. It generates electricity at its combined heat and power plant and at small-scale hydroelectric plants.
L.Tech Slovakia’s assignment at the Karlskoga plant covered two areas of the boiler system: the replacement of tube wall panels and major work on the economiser, including the replacement of convection coils and finned-tube economiser sections.
Project Scope
Our team removed the existing boiler tube wall panels and installed the replacements. For the economiser works, we cut the old convection coils approximately 50 mm from the header, lifted them out and fitted the new coils in the available space.
The scope also included removing and installing the finned-tube economiser sections. Their size and weight, combined with the limited clearance around them, required a series of carefully planned lifts and strict safety controls throughout the work.